The evaluation framework recommended in this report is illustrated in a flowchart format presented in Figure ES-1. The location in the main report of each item in the flowchart is identified in the figure. There are five steps in the framework.
Step 1 – Select Material and Application
The first step in the framework process is to select a material and an application (e.g., use blast furnace slag in embankment construction) and submit the application to the evaluator or decision maker. In most cases the evaluator or decision maker(s) will be the State transportation and/or environmental agencies.
Step 2 – Define and Evaluate Issues
The second step is to collect all relevant information that can provide input into the decision-making process. This includes, for the material and its proposed application, all related historical data, engineering and material property data, environmental, health and safety data, implementation constraints, recycling issues, and economic issues.
The purpose of this step is to define all issues that may warrant more detailed examination and in particular those issues that may be problematic insofar as approval of the material for use may be concerned. Recommended checklists to ensure that the proper information is collected for such an evaluation are provided in Chapter 2, Purpose and Methodology.
Step 3 – Stage 1 Screening Evaluation
The third step in the process is a Stage 1 screen. The purpose of a Stage 1 screen is to determine whether the data collected in Step 2 are sufficient to approve (or reject) the proposed application without additional study. A Stage 1 approval means that the evaluator has a high degree of certainty that the applicant has provided sufficient information to justify acceptance of the proposed material and application. The applicant will typically be required to demonstrate that the proposed material is sufficiently similar to reference materials, which have been used successfully, to warrant approval.
A Stage 1 screen should include an assessment of all existing data pertaining to engineering data, environmental health and safety, data recycling issues, implementation concerns, political issues, and economic issues to ensure that the data are sufficient to permit a responsible decision. A series of recommended screening checklists, evaluation procedures, and evaluation criteria is presented in Chapter 3, Screening.
Step 4 – Stage 2 Laboratory Evaluation
A Stage 2 laboratory evaluation is recommended if a Stage 1 review determines that existing information is insufficient to either accept or reject the application. The Stage 2 evaluation screen is intended to characterize (1) the engineering and materials properties and (2) the environmental, health, and safety properties of the proposed recycled material and its application product. These data can then be compared with established criteria or with the performance of reference materials using available laboratory and analytical engineering and environmental protocols.
To undertake a Stage 2 laboratory evaluation, it is recommended that (1) a test plan be prepared that delineates the samples to be tested and the tests to which the sample will be subjected, (2) acceptable specifications or performance criteria be identified that can be used as a means for evaluating the results of the test plan, and (3) the data be statistically evaluated to determine if specifications are met or if performance is similar to appropriate reference materials.
The most critical steps in a Stage 2 evaluation are development of the test plan and establishment of performance criteria. The main framework document provides a description of engineering and environmental parameters that will typically be of interest to decision makers when evaluating the use of proposed materials in specific applications and provides detailed lists of applicable laboratory test methods that can be used in the evaluation. Engineering and environmental parameters and test methods are presented in Chapter 4, Engineering Lab Tests and Chapter 5, Environmental Lab Tests, respectively.
Step 5 – Stage 3 Field Scale Testing and Demonstration
A Stage 3 field test may be warranted if the available data are still inconclusive after both Stage 1 and Stage 2 evaluations. Stage 3 is intended to provide field-scale data on (1) engineering and material properties, and (2) environmental, health, and safety properties of the proposed recycled material and its application product. These data can then be compared with established performance criteria or with reference materials (e.g., a control section).
Both engineering monitoring and environmental monitoring may be required during a field trial. Engineering monitoring refers to field evaluation activities that are intended to identify construction and performance aspects that may be affected by the use of a new material. Environmental monitoring refers to field evaluation activities that are intended to identify impacts to nearby air, soil, and water resources, as well as to the health and safety of workers that may result from the use or performance of the material.
Both short-term and long-term monitoring activities may be required for each type of monitoring activity. Short-term monitoring activities are activities designed to evaluate how the new material might affect the application during the end-product production process, such as asphalt or portland cement concrete production, and during and/or immediately after construction. Long-term monitoring activities are designed to evaluate how the proposed application performs during the post-construction period and can involve a time period ranging from several years up to the design life of the application.
To undertake a Stage 3 evaluation, it is recommended that (1) a demonstration test plan be prepared that delineates the field monitoring requirements, (2) acceptable specifications or performance criteria be identified to evaluate results of the field demonstration, and (3) the data be statistically evaluated to determine if specifications are met or if performance is similar to that of appropriate reference materials.
Field monitoring activities will differ, depending on the type of application being proposed. Recommended engineering and environmental field monitoring activities are presented in Chapters 6 and 7, respectively.